OVERVIEW
What is A+B Bidding
What are the Benefits of
A+B Bidding?
Criteria
For Selection of A+B Bidding
Criteria
for Selection: A+B bidding without I/D provisions
What is A+B Bidding?
A+B Bidding is a cost-plus-time bidding procedure
that selects the low bidder based on a monetary combination of the
contract bid items (A) and the time (B) needed to complete the project
or a critical portion of the project.
What
are the Benefits of A+B Bidding?
Time Savings
A+B Bidding is used to motivate the contractor to minimize the overall
time on high prority and high usage projects. This encourages contractors
to finish early by (1) offering bounses for early completion and
(2) assessing fines for late completion.
Criteria for Selection
A.
Criteria for Selection: A+B bidding with I/D provisions
1. Traffic restrictions, lane closures, or detours
result in high road user costs (RUC). Some agencies specify a minimum
threshold RUC level ($2,000 - $3,000 per day). If the monetary benefits
to the highway user equals or exceeds the Contractor's costs to
finish early and earn the maximum incentive.
2. Safety concerns, or significant impacts to the
local community or economy during construction warrant expediting
the project.
3. Traffic control phasing can be structured to maximize
a contractor's ability to reduce the duration of construction.
4. The project is relatively free of utility conflicts,
design uncertainties, or right-of- way issues which may impact the
bid letting date or the critical project schedule.
5. It is in the public interest to complete the project
as soon as possible, or by a specific completion date and the agency
seeks contractors expertise to facilitate an earlier completion.
B.
Criteria for Selection: A+B bidding without I/D provisions
1. The project is not required to finish by a specific
completion date.
2. RUC is not severe but other special concerns warrant
expediting the project.